Congratulations to the team at Susquehanna on this achievement:
It was anything but business as usual when PPL Corporation reconnected Unit 2 of the Susquehanna nuclear power plant to the electrical transmission network early this morning (3/24).

It was business better than usual.

Employees and contractors safely completed a 26-day refueling and inspection outage - the shortest in the plant’s 20-year history.

"This achievement is the result of significant improvements to processes and planning that we have made over the past several years," said Bob Saccone, vice president-Nuclear Operations. "Employees thoughtfully reviewed and researched plant and industry experience to identify improvements that would not sacrifice safety."

The improvements include better planning, earlier inspection of equipment, performing more work simultaneously and using new equipment to perform routine tasks more efficiently.