Breaking News
Loading...
Tuesday, 23 September 2008

Info Post
Well, when anyone operates a first-of-a-kind, multi-billion dollar machine, they're bound to have hiccups. Here's CERN:
During commissioning (without beam) of the final LHC sector (sector 34) at high current for operation at 5 TeV, an incident occurred at mid-day on Friday 19 September resulting in a large helium leak into the tunnel. Preliminary investigations indicate that the most likely cause of the problem was a faulty electrical connection between two magnets, which probably melted at high current leading to mechanical failure. CERN ’s strict safety regulations ensured that at no time was there any risk to people.

A full investigation is underway, but it is already clear that the sector will have to be warmed up for repairs to take place. This implies a minimum of two months down time for LHC operation. For the same fault, not uncommon in a normally conducting machine, the repair time would be a matter of days.
And some more:
The time necessary for the investigation and repairs precludes a restart before CERN’s obligatory winter maintenance period, bringing the date for restart of the accelerator complex to early spring 2009. LHC beams will then follow.
Picture of a large dipole magnet lowered into the tunnel in April 2007. Source: Cosmos magazine; credit: AFP/CERN.

0 comments:

Post a Comment