Progress Energy Florida (PEF) has asked state regulators to approve increasing the output of the utility's Crystal River nuclear plant, a proposal that is expected to save billions of dollars for customers.Technorati tags: Nuclear Energy, Nuclear Power, Environment, Energy, Politics, Technology, Economics, Crystal River Nuclear Power Plant, Progress Energy
Increasing the plant's gross output from 900 megawatts (MW) to 1,080 MW will be enough to serve an additional 110,700 homes. (Based on approximately 615 homes per MW, the higher-output plant could serve about 664,200 homes.) Because nuclear energy is the most cost-effective way to generate electricity, the uprate is expected to save customers more than $2.6 billion in gross fuel costs through 2036.
Progress Applies for Crystal River Uprate